On January 30, the sixth day of the Lunar New Year, when everyone was still "dwelling" at home to prevent the virus, the construction site of the Xianghu New Town Branch of the First Affiliated Hospital of Nanchang University was in full swing. A group of workers wearing blue masks were busy backfilling the earth, and the indoor workers were also working hard. Why should they rush the construction period during the special period when the epidemic was serious?
The time was set back to 15:30 p. m. on January 28, and a special dispatch meeting was held urgently in the office of the epidemic prevention and control headquarters for the construction of the Xianghu hospital area of the first affiliated hospital of Nanchang university.
At the meeting, Fan Yaqiang, Deputy Secretary-General of the Provincial Government, conveyed the latest deployment of the Provincial Party Committee and the Provincial Government to prevent and control the pneumonia epidemic of novel coronavirus infection-the First Affiliated Hospital of Nanchang University Xianghu New Town Branch as a provincial designated hospital for the treatment of patients, 1# inpatient building To be put into operation in advance.
As the representative of the construction party of the project, Ding Guolao, deputy secretary of the party committee and general manager of Jiangxi Construction Engineering Second Construction Co., Ltd., took the order on the spot-before February 8, ensure that the wards on the 6th to 16th floors are delivered for use!
Hear the order and move. On the same day, Zhou cai, Secretary of the Party committee and chairman of Jiangxi Construction Engineering Group, made a request for this work: "during the epidemic prevention period, we should give full play to the role of provincial state-owned enterprises, charge ahead at the critical moment, coordinate and solve all kinds of problems in construction in a timely manner, complete the construction task ahead of schedule on the premise of ensuring quality and safety, and submit a satisfactory answer to the provincial Party committee and government."
Jiangxi Construction Engineering Group quickly set up a project work promotion team headed by veteran Comrade Ding Guo. On the morning of January 29, the project team held an emergency meeting in the project department to fully understand the construction of the project.
"Our advantage now lies in the fact that we robbed some construction periods before the holiday years ago, and the amount of work is not too much. Now our biggest problem is that the laborers are worried about the epidemic and it is difficult for teams to enter the site." Huang Fengping, executive project manager of the project, said. In the face of difficulties, the work promotion team quickly formulated a construction plan:
-- Tackling key problems in an all-round way. According to the construction situation of the project, the project team comprehensively sorted out the remaining workload of the 6-16 floors of the ward, arranged the construction period in reverse, defined the engineering nodes of each detail such as indoor decoration, water and electricity installation, outdoor engineering, etc., determined the work plan of delivering the ward in layers and stages, and arranged the work team to tackle key problems.
-Ensure that personnel are in place. In view of the difficulty of entering the site due to "road closure" and other reasons, the project department communicated with the relevant departments of the provincial government in a timely manner to open up a green channel for project construction personnel. As of January 30, more than 30 people have arrived at the construction line, more than 10 machines have been put into production, and the project is progressing in an orderly manner.
-- Ensure construction safety. Construction during the epidemic period should be specially protected. In response to the epidemic prevention and control of the construction site personnel, the project department communicated with the First Affiliated Hospital of Nanchang University in a timely manner to ensure the supply of masks on the construction site, and conducted temperature tests for the staff twice a day, and formulated emergency plans to ensure the construction site Safety.
"During the epidemic, the rapid construction of Wuhan Huoshenshan Hospital inspired each of our builders. Now that the task falls on us, we will certainly live up to the trust of the provincial government." Ding Guolao said: "From the current construction progress, everything is under control. We are still further improving the plan, taking every detail into account to ensure that the 11-story ward is successfully put into the epidemic prevention and fight."
(Tang Hong Wan Shu Fung)